Requirements
Removing wastes & carrying goods
Single gridline impact + ties on the concrete structure only (30 meters FS)
Use the hoist to carry the crane elements which is installed on the roof
Our solution
Scalable solution : 2 units of XMH double mast perpendicular hoists with 6 tons capacity, 40 m/min, 6.50m Depth and 2.50m Wide
3 months only from Design to On-site delivery